Best of LinkedIn: Charging & Battery Tech CW 46/47 2026

Power access now decides truck charging projects more than vehicles or chargers. California utilities had a median wait of 950+ days for EV charging power in 2024, while funded trucks already outnumber planned chargers. Operators respond with batteries, shared connections, portable chargers and early capacity applications. At the same time, fixed grid charges push public charging prices up and reshape the economics for operators.
Date
November 26, 2026
Charging & Battery Technology
Thomas Allgeyer

Methodology: Every two weeks we collect most relevant posts on LinkedIn for selected topics and create an overall summary only based on these posts. If you´re interested in the single posts behind, you can find them here: https://linktr.ee/thomasallgeyer. Have a great read!

Listen to our podcast

If you prefer listening, check out our podcast summarizing the most relevant insights from Charging & Battery Tech CW 46/ 47:

Grid Access Sets the Pace

  • Grid connection delays, not truck availability, are the main obstacle to building megawatt charging networks for long-haul electric trucks.
  • California utilities had a median wait of 950+ days for EV charging power in 2024.
  • California lets its big utilities take up to nearly nine years to build a new substation for a large truck charging site.
  • Electric Class 8 tractors can be ordered and delivered in months, so the grid becomes the long pole.
  • Grid connection, civils and utility coordination are harder to deliver than the chargers themselves.

Funded Trucks Outpace Chargers

  • California funded 1,630 Semis through HVIP, worth $244M in vouchers and 85% of the open Class 8 truck money.
  • Planned Megachargers fit about 1,000 trucks a night by 2027, against 1,620 Semis funded in California.
  • California subsidizes trucks heavily but gives far less money to the megawatt chargers those trucks need.
  • With California's ACF drayage fleet requirements repealed, port truck charging has to win on cost per mile.
  • Megawatts and energization timelines, not connectors, are expected to decide whether port truck charging succeeds.

Where European Truck Demand Lands

  • Europe's electric trucks will need about 100 TWh of electricity a year by 2035.
  • Depots take more than 70 to 80% of charging energy in most countries and scenarios.
  • The busiest 10% of locations could carry up to 90% of truck charging demand.
  • Peaks of 20 to 50 MW are expected at the biggest sites.
  • Because these sites are largely known today, operators can apply for grid capacity now.

Storage Works Around the Grid

  • Adding 50 MWh of storage to two Antwerp truck hubs puts spare grid capacity to work years before full demand.
  • Batteries can earn balancing revenue early, then absorb charging peaks as truck volumes grow.
  • In the US, demand charges of $15 to 30 per kW a month make standalone fast charging expensive.
  • Storage flattens peaks, and a Stockholm site ran 720 kW fast charging within a 200 kW grid limit.
  • A new 2 MVA connection can cost around £250,000 and take up to 12 months, so whole-site planning pays off.

Creative Routes to Faster Power

  • A Portsmouth driving school runs two electric artics from a portable charger on its existing three-phase supply.
  • Sharing connections with solar and wind parks and using flexible agreements can connect truck chargers sooner.
  • Overhead gantries let a UK depot charge four trucks from a 600 kW power unit without losing parking spaces.
  • Whole-site planning often reveals capacity a depot already has before any upgrade is requested.
  • Mapping demand profiles against local substation capacity can speed grid access instead of waiting for the operator.

Megawatt Charging Scales Up

  • A Torrance hub offers 9 MW and 50 ports with both MCS and CCS, opening mid-2027.
  • Tesla's first Semi Megacharger in Texas has eight stalls rated up to 1.2 MW.
  • Battery-electric trucks took 49.8% of China's new domestic heavy-truck registrations in September 2026.
  • Megawatt charging brings 1.05 MW peaks on a light-duty truck and about 100 km of range in around 6 minutes on heavy models.
  • Terawatt's four new fleet depots add a combined 22 MW, enough to charge more than 3,000 vehicles daily.

UK Grid Charges Lift Prices

  • A typical rapid charger now pays £440 a week in fixed grid charges, up from £61 in 2021.
  • Average rapid charging costs 79p per kWh today and could reach £1.03 in 2027.
  • Since 2022, sites have been billed on the power they could draw, not what they actually use.
  • At one Birmingham hub, electricity and grid costs take 48p of the 58p a driver pays before VAT.
  • Policy uncertainty and rising fixed charges make long-term charge point investment harder to justify.

Operations and Business Models

  • Charging is increasingly seen as an operations business, where grid connection, DC network and storage outlast the chargers.
  • Charging resellers could hold €33.6 billion yearly by 2035, delaying payments to operators who supplied the energy.
  • Average public charger utilisation in Germany is 13%, roughly three hours of work a day.
  • US public fast charging passed 80,000 ports and 50 million sessions, with installed ports up 25% year over year.
  • Electric truck cost competitiveness depends more on utilisation than on the truck itself.
Subscribe to newsletter

Subscribe to receive the latest blog posts to your inbox every week.

Please confirm your GDPR consent to join our mailing list.
By subscribing you agree to with our Privacy Policy.
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.

Frequently asked questions

What is the biggest challenge for electric truck charging right now?

Grid power is the main constraint. California utilities had a median wait of 950+ days for EV charging power in 2024, and substations can take nearly 9 years. Meanwhile 1,620 Semis are funded in California, but planned Megachargers fit about 1,000 trucks a night by 2027.

How can truck charging hubs avoid grid delays and demand charges?

Many operators add battery storage and plan whole sites. Milence is adding 50 MWh of storage to two Antwerp hubs years before full demand. Storage also helps sites dodge US demand charges of $15 to 30 per kW a month. A Stockholm site ran 720 kW charging within a 200 kW grid limit.

Why could UK rapid charging cost £1 per kWh by 2027?

Fixed grid standing charges are the cause, not the electricity itself. A typical rapid charger now pays £440 a week, up from £61 in 2021. The average rapid charge is 79p per kWh today and could reach £1.03 in 2027.

No items found.

Want to see the posts voices behind this summary?

This week’s roundup (CW 46/ 47) brings you the Best of LinkedIn on Charging & Battery Tech:

→ 70 handpicked posts that cut through the noise

→ 40 fresh voices worth following

→ 1 deep dive you don’t want to miss